The last public consultation will be held on 14th November (16.00-19.30hrs) at the Montessori School in Half Moon Lane. Some initial enabling work on underpinning the abutments started in September and the actual renewal works will take place in January and February.

The sections of road by the bridges in Croxted Road and Rosendale Roads will be closed to all vehicle traffic from Saturday 11 to Sunday 26 January (with a pedestrian walkway except for the actual construction works on the weekend of 17/19 January).

Village Way bridge will be closed to vehicle traffic from Saturday 8 to Sunday 23 February – the actual construction work will take place on the weekend of 15/16 February.